|
Written by Paul Mutter
|
|
Tuesday, 09 March 2010 10:24 |
|
Readers who were wondering what
progress was being made to put in
place the power supply to the new
desalination plant on the outskirts of
Torrevieja need wonder no longer
because, according to reports in
regional Spanish newspaper Información
last week, tenders are being issued
for the construction of a power plant
which will be located in the grounds of
the desalination plant itself. The cost of
the power facilities will be 11.8 million
euros. The capital cost of the
desalination project itself is 215 million
euros and when the plant is completed
and operational it will produce 80
hectometres of water per year
increasing eventually to 120 hectares.
The initial quantity is said to be enough
to supply two million people and
agricultural demands with half going to
each.
The project has been dogged by
delays. Initially there were objections to
the planning consent on environmental
grounds which had to be resolved in
the courts with the decision going in
the end to the national government for
the continuance of the project. Then
there were lengthy negotiations with
the Town Hall of Torrevieja before
consent was given to a route for the
inlet and exhaust pipes to follow and a
compensation package agreed. More
recently it was announced that work on
the pipe connections at the harbour
end would not be completed before
the summer and hence would have to
stop over the high tourist period as no
construction is allowed over those
three months. Other aspects of the
hugely complex civil engineering
project have been progressing
satisfactorily, such as the pipework
leading the desalinated water away
from the plant to the Pedrera reservoir
and other receivers which is almost
completed. The question, though, of
where the power to run the massive
plant would come from has remained
unanswered until now with many
perplexed as to why adequate
provision had not been made at an
earlier stage of the project.
Apparently no one is venturing to
suggest when the plant will be finally
finished and up and running, the
original completion date was the start
of 2008. Información itself is sticking
with early 2011, a date which it forecast
earlier this year.
|